Depot roads
18 & 19 are used for train cleaning – as our visit was during the evening peak
these were empty at the time of our visit.
However, new
roads are being built for train cleaning outside of the main shed so as to free
space in the main shed for train maintenance. This work is being funded by the
DfT in order to equip the depot for extra work for the forthcoming May 2011
timetable change. The new roads will have high platforms and canopies for
weather protection. They will also be equipped with cleaning points and water
supplies.
Depots road
20 to 23 are used for train maintenance.
Hornsey depot
is equipped with jacks able to lift carriages up to 23m in length – a whole unit
can be lifted simultaneously, though more normally one carriage is lifted at a
time.
In the
maintenance area, mobile roller-shutter ‘tool banks’ are available for the
fitters, which can be moved to the location they are working in. The tools are
therefore readily available at point of use. Some staff are trained to
undertake welding activities.
For each
depot road the 25kV OLE can be isolated independently so that the train it that
road can be safely worked on. Fall-arrest equipment is also provided for the
safety of staff working on train roofs.
The depot is
at its busiest between 19.00 and 06.00hrs. At the end of the day’s rush hour
trains progressively arrive at the depot for overnight cleaning and maintenance
from around 19.00.
Train Exams
Most exams
are undertaken on accumulated unit miles – A, B & F. A C4 exam which includes
bogies and drawgear overhaul is undertaken nominally every four years, though
the exact interval depends on miles run by the unit.
A Class 313
has an exam every 4200 miles – which is normally after around three to four
weeks of operation. Mileage between exams and the normal duration between those
exams varies depending on the class of train.
Mobile boards
adjacent to the trains detail level 5 overhaul progress for the trains concerned
undergoing this activity
Bogies
requiring overhaul are sent to Railcare at Wolverhampton for class 313 units and
to Bombardier at Crewe for all other units.
Train
Modifications
The fleet has
had the First Capital Connect external branding applied following the take-over
of the Great Northern franchise from National Express West Anglia and Great
Northern. The supplier of the train external vinyls also applied this to the
trains after the train bodies had been thoroughly cleaned and prepared.
First-of-class fitment will be carried out by the depot to replace Cab Secure
Radio with the new Network Rail Global System Mobile – Rail (GSM-R) train radio
as the GSM-R network progressively comes live over the next few years.
Blue Room
The blue
room, so named due to the colour on the walls, is used to give a quick visual
view of depot performance. Each department in the depot has its own board.
Examples of boards include those on the status of materials; various projects in
progress; a technical issues board showing progress on delivering improvement in
reliability to the fleet, a generic depot performance board and a board
detailing train fleet performance. The train performance boards shows miles per
causality for each train class maintained at Hornsey and is updated weekly.
The Blue Room
adjoins the main depot office and some boards can be turned round so as to be
visible from either room.
The boards in
the room are reviewed every day at 10.00 by the Depot Manager.
Main Office
Next to the
blue room was the main depot office, which is occupied by a number of different
posts.
The Fleet
Manager’s position is manned over three shifts per day. Amongst other duties
they take calls from drivers who are experiencing difficulties with their train
which they try and resolve over the phone were possible. Drivers either report
faults by their company issued mobile, or can be ‘patched’ to the depot by the
signaller when using Cab Secure Radio, though this can time-out after a while,
requiring the call to be restablished. Drivers also report faults which are not
immediately service-affecting. Rectification of some faults can be deferred,
others not. Faults which have been reported by drivers, along with their
priority, are shown on a white board. Some faults can temporarily be dealt with
so as to keep the train in service for the rest of the day. For example, a cab
fault can temporarily be mitigated by being ‘boxed in’ – that is placing the
faulty cab in the centre of the train when coupled to another unit. However,
care then needs to be taken to ensure that train then subsequently doesn’t get
split during the rest of the day’s service.
The
Operations Manager plans the unit allocations to ensure trains get to the depot
when they should for examinations. Train diagramming is based on miles to next
exam. For example, if the depot is busy, a unit maybe put on a low mileage
diagram so as delay its coming into the depot for an exam by a day or so.
The Shift
Fleet Manager organises the maintenance plan for the units. A board on the wall
shows the plan for the next seven days.
Servicing and
Test Room
As seems to
be increasingly the trend, more and more component repair and overhaul works are
being undertaken ‘in house’ by depots rather than by external contractors . As
well as improving quality, being able to repair equipment in the depot reduces
downtime.
As train
fleets ages problems with component obsolescence increase. Interesting, this is
less of an issue with the older 1970s and early 1980s trains compared with those
built more recently. On the older trains, whilst supplies of an original part
may disappear, it is usually possible to ‘backwards engineer’ a part so that it
can be manufactured by someone else. However, this is not possible with the
electronics and now software used on more modern trains. For example, the
electronics used on Class 365s units are now causing concern and the
installation of new traction equipment to these trains at mid-life overhaul is
currently being considered. The Class 377s use Windows 98 software on the
various computers on the trains.
There is some
commonality of components between units of similar vintage, for example some
relays are ‘common’ between Class 313 and Class 317s.
Wheel Lathe
At the time
of our visit the original wheel lathe was still in use. This is only capable of
turning a single wheel at a time and requires considerable time to be set-up for
each wheel to be turned.
However when
we visited a new German lathe, installed by Network Rail, was nearing completion
and was planned to be commissioned by early May 2011. The new lathe includes a
battery tug to manoeuvre the trains and will be able to turn multiple wheels at
once. The new lathe is computer-controlled enabling quick configuration of the
correct wheel profile of the wheels to be turned.
In the
meantime the old lathe is being ‘nursed’ until the new one is available. When
the old lathe is decommissioned the building will be refitted with heavy lifting
equipment to enable traction motor changes to be carried out.
Stores
The depot
stores are housed in the old steam engine shed – one of the original parts of
the depot still surviving. Battery tugs are used to move bogies and other heavy
equipment around the depot.
Depot
Shunters:
Two diesel
shunters were on the depot at the time of the visit:
03 179 – this
shunter was formally used on the Isle of Wight and therefore has a cut-down cab
for use through the restricted height of Ryde tunnel. This shunter has a
mechanic gearbox. The locomotive is retained as a ‘depot mascot’, though is
unfortunately its compressor is too underpowered to pump-up the brakes of modern
EMUs in a reasonable time, so it of not much practical use at the depot.
08 750 – this
350hp diesel electric shunter was being hired from Wabtec due to problems with
the tugs which are normally used to manoeuvre carriages within the depot.
Driving
Simulators
After
Ladbrook Grove, it was recommended that driving training and assessment was
improved using new technologies including driver simulators. First Group was
one of four companies to introduce simulators following this recommendation.
The tender for the simulators at Hornsey was won by Krauss-Maffei Wegmann GmbH (KMW)
of Germany bwhich had history of developing simulators for the military – tanks,
trucks etc. They have since moved into train and lorry simulators.
Ł900 thousand
was spent on the simulators at Hornsey. The simulators were commissioned in
early 2009. The simulators have been well received with the technology and
craftsmanship considered excellent Two simulators are installed at Hornsey, one
representing a class 319 EMU used on the Thameslink route, the other a class 365
EMU as used on the Great Northern route from Kings Cross to Peterborough and
Kings Lynn.
On the class
319, the AC/DC power changeover, which trains on the Thameslink route undertake
at Farringdon, can be simulated. The controls on the new classes of unit are
significantly different with the class 319 having a separate power and brake
controls whereas the class 365 has a combined power and brake controller – more
on these later. For both classes of train each simulator consists of a very
close reproduction of the actual train cab, including the virtually the same
dimensions from side to side and from front window to rear bulkhead as the
‘real’ cab so as to be as realistic as possible. A screen shows the image of
the line ahead through the driver’s front window and other screens are placed by
the cab side windows to show the view the driver would see from these,
particularly when using Driver Only Operation CCTV from station monitor banks.
For the
auxiliary cab-switchgear, touchscreens are used to simulate the switches rather
than an attempt made to simulate the 1980s switchgear used in the actual train
cabs which would have been problematic and a likely source of failure. Also
using propriety touchscreens enables easy replacement if a screen fails – only
four screws are required to remove a screen. Touching a picture of the switch
on the touchscreen simulates switch operation.
New friver
training consists of a 22 weeks in the classroom, including time on the
simulators. Some 600 drivers have now used the simulators. As well as being
used to train new recruits, they are also used to retrain drivers after
operational incidents, for training as an aid to understanding of rules and
regulations and for the enactment of hazards and their control measures. The
simulators are now used as part of drivers bi-annual appraisal process. No
driver has yet said that the simulators have not taught them anything – they are
considered a benefit by all.
The simulated
route consists of 100km of generic route. It is considered best to use a
generic route rather than attempt to simulate a ‘real’ route as if an actual
route was used drivers would find inaccuracies with the route and be distracted
by this which is not the point of the simulator. Multi, double and single track
lines are simulated as well as two, three, four aspect and junction signals.
Different weather conditions can also be simulated as well as different light
levels depending on the time of day. Additionally, adhesion levels can be
varied so that correct braking technics in poor adhesion conditions can be
experienced. The simulator includes a comms platform so that the Cab Secure
Radio in the cab can be set-up and used during the driving simulation and
safety-critical communications protocol exercised. A refresh of the simulators
will add simulation of the new national train radio system GSM-R.
Drivers using
the simulators have been seen to wave at simulated trains passing them – which
is measure of how realistic the simulator is compared to driving a real train!
Train faults
and PASSCOM activations on the train can also be simulated. Touchscreens
outside of the cab can be used for drivers to ‘isolate’ cocks etc around a
virtual train, which utilises images from actual trains.
In early 2010
signallers from Peterborough Signalling Control Centre had a go at using the
simulator to get an appreciation of what the drivers’ experience. This is going
to be repeated for signallers from Kings Cross and West Hampstead Signalling
Control Centres.
Driving the
Simulators
The Class 319
cab has separate power and brake controllers – each consisting of a handle
perpendicular to the driver’s desk which is moved through an arc. The brake
controller is on the driver’s left hand side, has four steps: 1, 2, 3 – Full
Service, 4 – Emergency. There is a two minute delay after an emergency brake
application before the brakes can be released. The power controller is on the
driver’s right-hand side.
On the Class
365 there is one combined power and brake controller on the driver’s left-hand
side. This consists of a ‘handle’ mounted one side of a post which is moved
towards or away from the driver to apply power and brake respectively. There
is a distinct ‘notch’ between power and brake positions where the controller
slightly moves from side-to-side through the transition. So that power can be
applied to start a train whilst on hill, there is a ‘hill start’ button on the
end of the handle which can be depressed to keep the brakes applied until power
is available. So, when starting a train on hill, the button is depressed, the
handle moved from the brake position to power and then when the train starts to
apply power, the button is realised.
We each had a
go at driving both simulators between a number of stations. It was quite
noticeable that the Class 365 was significantly ‘nippier’ than the Class 319,
acceleration notably quicker.
On both
trains, there is driver reminder appliance (DRA) button in a prominent position
at the top of the ‘dashboard’ below the windows. This is depressed: when the
driver is closing down, entering or leaving the cab or when the driver does not
have authority to proceed – for example at a red signal. When depressed, the
button glows red and prevents traction power being applied. When the driver has
authority to proceed the button is pulled outwards extinguishing the light and
allowing traction power to be applied. The DRA buttons were mandated after a
series of accidents, many caused by the driver being distracted during station
duties and then forgetting, or not checking, the signal aspect when the train
was ready to depart. The DRA helps prevent this as this button should be
realised as the last action the driver undertakes before leaving a station.
For a station
departure, as with when driving a real train, when driving the simulator we had
to: check the signal is clear; look out of the window at the DOO CCTV monitor
bank to check that no passengers are going through the doors; press the door
close buttons; hear the door close ‘hustle’ alarm and watch the doors close and
body side orange indicators light extinguish on the DOO CCTV image; check that
interlock light on the desk illuminates; cancel DRA, realise brakes and apply
power.
A PASSCOM
(passenger communication alarm) activation was simulated whilst we were driving
the simulator. The touchscreens outside the cab were used to see which coach
had the orange bodyside light lit – which indicates that it was the coach where
the PASSCOM activation was made. Once that coach is selected the applicable
coach interior views are then displayed so that the individual PASSCOM alarm can
be reset.
Whilst we
were driving the simulators we also had to deal with various hazards, such as
falling snow, low adhesion, passengers trapped in doors, a broken windscreen and
other members of the Institution in the cab giving driving ‘advice’!
Finally, on
behalf of all the Institution members which took part in the visit, I would like
to convey a grateful thanks to all Richard Farish and all his colleagues from
First Capital Connect which took time to show the Institution around the depot,
answer our many questions and gave us a generous amount of time to drive the
simulators. A very enjoyable and interesting evening was had by all.